Coastal projects advancing this year

January 22, 2018 by Morganza Action Coalition

By:  Holly Duchmann, HoumaToday.com

 

Southeast Louisiana has nearly $1.2 billion in coastal restoration and protection projects that are completed or in the process of completion, including multimillion-dollar improvements for Terrebonne and Lafourche parishes this year. 

The projects include:

Whiskey Island

Construction to rebuild Whiskey Island, a barrier island in Terrebonne Parish, began in March of last year and the project is on track to be finished this April, Terrebonne Parish President Gordon Dove said last week.

Ten million cubic yards of sand are being pumped onto the island as a part of the $103 million project. It is 65 percent complete with 7.5 million cubic yards of sand pumped so far, Dove estimates.

The island helps protect the parish from the tides of the Gulf of Mexico. The tides, with their high salt levels, have been slowly eating away the parish’s marshes, Dove said.

Cut Off/Pointe-aux-Chenes Levee

This $9.5 million project aims to improve more than two miles of existing levee near Cut Off in Lafourche Parish.

Construction is to continue through 2018.

Falgout Canal Floodgate

The $35 million Falgout Canal Floodgate in Dularge is under construction and should be finished in January 2019, though Dove said officials are are trying to speed it up for this upcoming hurricane season.

The 195-foot floodgate is “the final linchpin” for the Morganza-to-the-Gulf system from Bayou Dularge to Pointe-aux-Chenes, where the parish is most vulnerable, Dove said.

“We’ve made a lot of strides,” Dove said. “This didn’t happen overnight. It’s taken years to come to fruition and it’s a great thing for the future of

Restoration and Planting in the Des Allemands Swamp

Construction for this 2,395-acre project began last fall and is expected to be finished this spring.

Along with planting cypress and tupelo seedlings, this project will enhance drainage in the swamp, which is located south of Vacherie.

Once complete, the $7.8 million project is expected to benefit local wildlife and fish, as well as assist in storm buffering.

Filed Under: News Articles

Primary Sidebar

Recent Posts

  • Corps Breaks Ground on New Humble Canal Floodgate
  • Morganza Minute – December 2022 E-Newsletter
  • U.S. Senate Approves $19 Million for Morganza in Spending Bill
  • $19 Million for Morganza Included in Federal Appropriations Bill
  • Gov. Edwards Touts MtG in Senate Testimony

Archives

  • December 2022
  • March 2022
  • February 2022
  • January 2022
  • November 2021
  • August 2021
  • February 2021
  • August 2019
  • July 2019
  • June 2019
  • February 2019
  • January 2019
  • December 2018
  • October 2018
  • September 2018
  • August 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • January 2018
  • December 2017
  • July 2017
  • April 2017
  • February 2017
  • January 2017
  • November 2016
  • October 2016
  • September 2016
  • August 2016
  • July 2016
  • June 2016
  • May 2016
  • April 2016
  • March 2016
Sign the Petition

Join Our Mailing List

Footer

MAC

Morganza Action Coalition is the voice for the residents of Terrebonne and Lafourche Parishes, Louisiana as we push for hurricane and flood protection that our community needs and deserves.

CONTACT US

Morganza Action Coalition
henri@morganza.org
(985) 258-1399
P.O. Box 2601
Houma, LA 70361

JOIN US

Support MAC
Join Our Mailing List

Copyright © 2023 Morganza Action Coalition. All rights reserved.